Error and Notification Messages
www.3ware.com 287
See Also
“Viewing Current Task Schedules” on page 174
“About Initialization” on page 158
003D Verify paused
Event Type
Information
Cause
The verify operation is paused.
Verifies are normally paused for 2 (formerly 10) minutes after a system first
boots up. Verifies are also paused during non-scheduled times when
scheduling is enabled.
Action
If you want the verification to resume, you can disable or modify the schedule
through 3DM or CLI
See Also
“About Verification” on page 162
“Scheduling Background Tasks” on page 173
003E Migration paused
Event Type
Information
Cause
Migration is paused. Migration follows the rebuild schedule.
Action
If you want the migration to resume, you can disable or modify the schedule
through 3DM or CLI
See Also
“RAID Level Migration (RLM) Overview” on page 128